Question 12099 of 749 · Maryland Journeyperson Electrician Exam

An existing 200 A service shows a 1-year maximum demand of 110 A. A 40 A load is added. Using NEC 2020/2023 220.87, what is the resulting calculated load?

Exactly one answer is correct.

Show solution

Correct answer to question 12099

  • C: 177.5 A

Explanation

220.87 takes the 1-year maximum demand at 125 % and adds the new load: 110 x 1.25 = 137.5 A, plus 40 A = 177.5 A, which the 200 A service can carry.