Question 2029 of 749 · Maryland Journeyperson Electrician Exam

Where must the service overcurrent device be located relative to the service disconnect?

Exactly one answer is correct.

Show solution

Correct answer to question 2029

  • A: Part of the service disconnect or immediately adjacent to it

Explanation

The service OCPD must be an integral part of the service disconnecting means or located immediately adjacent to it. See 230.91.